1. INTERPORT has completed the "Technical and Economic Feasibility Study of Payra
Port" as sub consultants to HR Wallingford: HR Wallingford with its partners study
analysed the existing environmental and site conditions, to determine the best
navigation route and to develop the overall concept master plan of the proposed
port in the context of the requirements of the port Authority, the potential
market and the economic feasibility of possible development opportunities.
2. With HR Wallingford INTERPORT, completed several short time studies for the Government of Bangladesh
3. With HR
Wallingford INTERPORT, were retained by the Bangladesh Navy, to assist in the
development of new pontoon berthing facilities in Chattogram. The scope of work included master planning
and concept design, construction execution planning and scheduling, detailed
design and specification and technical support during construction for the
berth protection dolphin structures to mitigate the risk of vessel damage at
berth in the event of drift collisions.
4. In the UK, INTERPORT has recently completed a series
of ferry and international logistics
studies for several clients.
5. Special
Jetty including causeway at Cox's Bazar Inani Area (IFR): As CORE consultant to Bangladesh Navy,
INTERPORT was engaged in Consultancy, Supervision and to provide detail design,
drawings and estimate for a 830m steel piled jetty for the Bangladesh Navy
Fleet review. A series of 22.5 spans were design to withstand traffic load from
shore to the berthing platform.
6. Hydrologic
and Hydraulic Study in the Karnaphuli River as sub-consultant to HR
Wallingford: The overall aim
of the project was to evaluate the potential for development of Chittagong
Port, balancing the physical characteristics and constraints of the Karnaphuli
River and the opportunities to develop and grow port maritime traffic and cargo
throughput.
7. Design &
Construction of Jetty 3 & 4 in Mongla Port as sub- consultant to HR
Wallingford: In order to
expand capacity the Mongla Port Authority is extending its current terminal
south with the construction of 6 additional bays to establish Jetty 3 & 4
to allow Panamax size vessels access, loading and Unloading.
8. Asrayan-3,
Development of BhasanChar, INTERPORT working as sub-consultant to HR
Wallingford: HR Wallingford
and the Associate INTERPORT were retained by the Bangladesh Navy to undertake a
feasibility study, concept design and detailed design work for a 12km long
interim stage flood defence embankment and associated shore protection works on
the Island of BhasanChar, northern Bay of Bengal.
9. BIEZL Marine
Terminal, INTERPORT is engaged as sub-consultant to HR Wallingford: The Bashundhara Group proposes to construct a
multi-purpose marine terminal near its new steel mill. HR Wallingford in
association with INTERPORT is responsible for concept design and construction
support for the dry bulk import terminal including supporting marine studies.